Why does the IDNO need to know the POC before they can provide a price?

Q:

Why does the IDNO need to know the POC before they can provide a price?

A:

We need to know where the new network will connect to the existing mains network so that we can provide a design and price for the offsite works as well as the onsite network installation. This is known as contestable works. The final connection to the existing electricity network is non-contestable.

See also: IDNO vs DNO